Construction period: 
2013
Project owner: 
Tpf Econoler
Project

TPF-Ecoloner s.a. is responsible for the design, supply, installation and commissioning of a second grid connected wind farm system on the Ngong Hills, in Kenya. The 8 wind mills are Vestas V52 (850 kW) generators with a tower hub height of 49m. The foundation is a square concrete plate of 11m side, from 95 to 115cm high, put at 2m below ground level, connected by a steel tube to the tower.

Assignment
SECO’s assignment includes:
  • Analysis of the available soil data and, if required, make recommendations for additional tests.
  • Checking of the design of the foundations, according to the supplies specifications and following European standards.