Jerudong Park Marina Project - New breakwater

Jerudong
Brunei Darussalam
Construction period: 
1996-1998
Project owner: 
AMEDEO DEVELOPMENTCORPORATION
Amount of the works: 
€ 112.500.000
Project

The project consists in the construction of a safe harbour on the open coast of Brunei Darussalam along the Chinese Sea, South-East Asia.

The design concerns a rubble mound multilayer breakwater mainly capped by a concrete combined roadway/wave deflecting wall. The main breakwater structures reaches into the sea for about 2,5km up to a maximum depth of 9,4m. Within the sheltered area of the harbour several wharf structures and jetties were provided.

Assignment

The technical inspection performed by SECO concerned the design and the execution of the civil engineering part of the project.